India’s 2MW Solar + Storage Tender Date Extended.
Earlier in July, SECI had issued a tender for setting up of 2 MW Solar PV power plant with 01 MW BESS at KAA, Himachal Pradesh.
The last date of bid submission is now extended till 12.11.2018 (14:00 Hrs). The tender said that any containerised battery technology can be used as long it is suitable for the location’s climatic conditions.
The tender said that the battery will be located at Rangreek, Kaza near Rong Tong Hydro Power Station, 12,000 feet in altitude. The annual temperature of the location ranges of -40°C to 30°C and area sees snow of up to six feet in winter months. The tender also mentioned that the battery must be designed for maximum flexibility with regard to site-specific voltages, frequency, phase imbalance, and protection requirements.
The scope of work includes the design, engineering, supply, construction, installation, testing, and commissioning of the projects. Apart from these, the successful bidder will also be responsible for 5 years of operations and maintenance (O&M) services. This would include the supply and storage of all mandatory spare parts, consumables, repairs and replacements of any defective equipment during the O&M period.
SECI released the NIT on behalf of Himachal Renewable Limited, a JV between SECI and Himachal Pradesh State Electricity Board (HPSEBL).